| Client |
Melbourne Textiles Washing
Plant (P)Ltd |
| Project |
ETP for Textile Effluent |
| Role |
Project Management Consultants
for |
|
1. Study of existing practices of in-house
generation of effluents |
|
2. Effluent sampling, analysis and statistical
validation of design basis |
|
3. Laboratory treatability study for
desalination |
|
4. Laboratory batch scale multi stage
precipitation studies and establishing dosages |
|
5. Developing treatment process for potential
zero discharge upgrade later |
|
6. Demonstration of technologies in pilot
plants |
|
7. Preparation of tender document and
evaluation of tenders |
|
8. Inspection and certification of equipments
and off-site deliveries |
|
9. Certifying specific alignments of
high speed centrifuge systems |
|
10. Interactions with client, civil and
equipment contractors & P C Board |
|
11. Supervision of construction, trial
run, test run and commissioning |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Status |
The ETP has been commissioned in August
2005 and the RO segment will be taken up in 2006. |